Operations & Maintenance

District Maintenance Map

 

Operations and Maintenance Plan

2026 Operations and Maintenance Plan [Schedules are subject to change]
 

January

·         Finalize O&M contracts

·         Issue O&M Plan

·         Monthly well meter readings and reporting with BBA

February

·         Ditch and storm structure maintenance as necessary

·         Assess maintenance needs for any new scope areas in 2025 and beyond.

·         Assess need for and complete non pot forebay sediment removal (bi-annually)

March

·         Coordinate new user non pot meter installation as necessary

·         Update non pot user info and lists – assess and perform meter maintenance as needed

·        Begin tracking augmented water from wells and Whitney Ditch and submitting State augmentation reporting with BBA

April

·         Activate irrigation system and non-pot pump station begin providing water to users by April 20th

·         Turf aeration

·         Spring fertilization

·         Begin tracking and billing of non-pot water users

·         Fill forebay from Whitney Ditch if Poudre River declares free river

May

·         Begin mowing and weed control of native areas and ROW/field mowing

·         Complete cleaning of pump station facility

 

 

June

·         Plant replacements, if necessary

·         Assess, price, and perform various sign maintenance needs

July

·         O&M scope review/pricing requests

·         Update replacement reserves

·        Street sweeping as needed

·        Assess pricing and determine needs for bidding maintenance services

August

·         Site visit with district manager and board representative(s) for budget preparation

·        Draft 2027 O&M budget

September

·         Fill forebay prior to Whitney Ditch shut down

·        Final tree replacements, if necessary

October

·         Winterize irrigation system

·         Finish right-of-way mowing

·        Activate wells and fill forebay for shoulder season water as necessary

November

·         Finalize 2027 O&M budget.

·         Winterize non-potable water pumps

·         Submit State augmentation year-end report

·        Final storm structure maintenance

December

·         Update service area maps

·         Issue 2027 O&M contracts

·         Draft 2027 O&M plan


 